Media Studies · Shoot Guide
Media Studies · Component 1, the Foundation Portfolio · the storyboard, the shot list, the recce, the call sheet, the gate and the three windows
Read this first
Principal photography begins after the production-readiness check. Preliminary exercises and small tests happen before it. December 23 is the main gate and January 8 the repair opportunity. Bring a workable storyboard/animatic, shot and sound plans, tests of difficult setups, confirmed cast/locations and permissions, equipment access, actual shoot dates, risks, backups and a fallback.
January 24–February 21 is the main filming window. Aim to return with all principal footage so spring can focus on editing, reflection and the written paper. Approved late-December filming remains possible when cast/locations depend on school. The first two spring weekends are for limited pickups or failed shots. Missing the January 8 gate does not automatically move all principal photography to spring: resolve the readiness problem before the break.
| Window | Purpose |
|---|---|
| Approved late December | Filming that depends on school-based cast or locations, after the gate. |
| January 24–February 21 | Main independent production, on each student’s agreed dates. |
| First two spring weekends, provisional | Limited pickups or corrections identified through footage review. |
Declare intended dates at the December 11 clinic and confirm them at the gate. The filming pack organizes the month with a concise production record and light C2 retrieval. About 9–12 hours across the month is a starting guide for the whole subject workload; check the real requirements of your individual plan.
Feedback on your assessed opening
For assessed C1 work, teacher and assistant feedback identifies general strengths, limitations and requirements. You lead discussion of possible amendments and choose what to change. A teacher can demonstrate a technique on an unrelated example, but cannot prescribe your shot, edit, script, design or reflection. Detailed instruction remains available for separate preliminary exercises and exam practice.
1. The storyboard grid
Draw one frame per shot. You can use stick figures. Include arrows to show movement.
Under every frame, five lines:
| Line | Example |
|---|---|
| Shot type | close-up |
| Angle | low |
| Movement | slow tilt up |
| Sound | footsteps, no music |
| Seconds | 4 |
Draw the title and each credit into the frame where it appears, in the font from research 2.
How many frames. Draw each shot that you need. Twenty to thirty-five can be a useful starting estimate, but there is no required frame count. A long take may need fewer frames; a fast sequence may need more. Add the durations and keep the opening at 120 seconds or fewer.
The test. Give a frame to someone who has not read the script. Can they tell what the camera does? If not, a label is missing.
2. The shot list
Put the storyboard shots in shooting order. Use one line for each shot:
| # | Frame | Location | Who | Equipment | Light | Sound | What could go wrong |
|---|
Two more lines at the bottom:
- The shot I would cut if I lose an hour.
- The shot I am most worried about. Shoot that one first.
3. The recce sheet
Walk the location with a phone before the shoot. Come back with:
- five or more photographs of the place
- a use for each spot: which frames happen here
- the light at the time of day you will shoot (what time is sunset in your window?)
- the sound problems: traffic, a fan, a corridor, a road
- one risk for each use, and what removes it (a wet floor, a road, a height, the dark)
- the permission: who said yes to you filming here, and when
Post it. The moderator reads the recce as planning.
4. The call sheet
One for each shoot day. Cambridge’s moderator asked for exactly this.
| Date and window | |
| Call time | when everyone arrives |
| Location, and how to get there | |
| Shots, in shooting order | frame numbers, from the shot list |
| Who is needed for each shot | |
| Equipment | from the sign-out sheet |
| Light | what time you must finish outside |
| Sound | the problem at this place, and the fix |
| Contacts | Contact details on the private crew copy; omit phone numbers from the blog copy. |
| The shot to cut if an hour is lost | |
| Wrap time |
Post the planning copy before the shoot day, with private contact details omitted. Keep the complete contact sheet available to the crew. Post the day’s stills and what you decided after it.
5. The gate sheet
Wednesday December 23. Bring this evidence for the readiness check:
- The animatic: your storyboard frames, cut to their seconds, with a temp track. Under 2:00
- A call sheet for each shoot day
- Cast confirmed: names, a message from each one saying yes, the dates they are free
- Locations confirmed: the permission, the time of day, the recce photographs
- Equipment/access and dates confirmed, with your shot/sound plan, backups and a fallback for an absent actor or failed location
- Risks, permissions and difficult setups checked, with relevant test evidence
You are approved to shoot when the readiness evidence is complete. If anything is missing, complete it and show the completed evidence again on Fri 8 January.
On the shoot day
- Shoot the shot you are most worried about first.
- Shoot every shot twice, and once more with something different.
- Record 30 seconds of the room with nobody talking. You will need it in the edit.
- Back up the footage in two places before you sleep.
- Post before you sleep: the call sheet, three or more stills, what you decided on the day and why, the shot you did not get.
After the shoot
The provisional spring sequence is footage audit/assembly in the February 22 week, rough cut in the March 1 week, screening/response in the March 8 week and revised cut/individual CCR in the March 15 week. March 26 is the internal target for the complete film, blog and individual CCR. April 23 is the coursework-administration and written-exam-readiness target. These are local targets; confirm the school calendar, Qingming week and external deadlines. The spring plan gives the sequence.
Where this comes from
The coursebook’s pre-production chapter, and the two blogs Cambridge published, counted in the blog recipe. The five-line storyboard label and the frame count are mine. Ask me about any of them.